Free template

Free capacity planning template for teams (Excel and Google Sheets)

A capacity planning template compares the hours your team actually has with the work assigned to it. This free template starts from real available hours, after meetings, time off and admin work, then flags who is over or under capacity each week. It works in Excel and Google Sheets.

Written by Intelogos. Last updated .

Team capacity calculator

How many hours does your team really have?

Fewer than the contract says. A team of six on 40-hour contracts has 240 hours a week on paper, but after 48 hours of meetings and admin and 16 hours of time off it has 176. Move the sliders to run your own numbers; the template does the same sum per person, per week.

Your team this week

6 people
40 hours
8 hours
16 hours
32 hours

Available hours

176

of 240 contracted

Utilization

109%

Over capacity

Contracted hours (6 × 40)
240
Minus time off
-16
Minus meetings and admin (6 × 8)
-48
Available hours
176
Work planned (6 × 32)
192

On paper, 192 planned hours fill 80% of contracted hours. Against the 176 hours the team really has, they fill 109%: 16 hours over capacity.

The basics

What is a capacity plan?

A capacity plan compares the hours each person on a team has in the coming weeks with the hours of work planned for them, so you can see overload before it happens and move work while there is still time. It looks forward, week by week, and it works in hours, because hours are what time off, meetings and estimates are measured in.

  • Capacity

    Hours people have

    Contracted hours minus time off and minus recurring meetings and admin, per person and per week. The template calls this available hours.

  • Demand

    Hours of work planned

    The estimated hours of project work assigned to each person in each week, added up across projects. The template calls this assigned hours.

  • Utilization

    Demand ÷ capacity

    The share of available hours the plan fills. Above 100% someone is over capacity; well below it, they have room for more work.

Five steps

How do you use this capacity planning template?

Fill in four sheets, one step each, and read the result on the fifth: your team, their time off, their recurring meetings and admin, and the work planned for them. Blue cells are inputs, every other cell is a formula, and dropdowns keep names consistent.

  1. 1

    List your team

    • Team

    Add each person's name, role and contracted hours per week, with part-time hours where they apply. Then set the first week of the plan on the Capacity summary sheet.

  2. 2

    Add time off

    • Time off

    Enter vacation, holidays, training and other absences as the person, any date in that week and the hours off. For a day off on a 40-hour contract, enter 8.

  3. 3

    Add recurring meetings and admin

    • Recurring meetings and admin

    List each person's standing commitments in hours per week: stand-ups, 1:1s, team meetings, email and reporting. A typical week in their calendar is the quickest source.

  4. 4

    Add the work

    • Work demand

    For each project a person works on, enter the estimated hours per week and the first and last week. If the hours change partway through, split the work into two rows.

  5. 5

    Read the summary and rebalance

    • Capacity summary
    • Weekly overview

    Red is over capacity, amber is under capacity and green is within. Move work from red weeks to people with spare hours, move dates, or agree on overtime openly, then review the plan every week.

Work demand

Sample data
ProjectPersonHours per weekFirst weekLast week
Website relaunchAna24Nov 2Dec 18
Website relaunchBen20Nov 2Jan 22
Mobile app updateBen16Nov 2Dec 11
Mobile app updateChloe30Nov 2Jan 22
Client onboardingDiego20Nov 2Jan 22
  • Instructions
  • Team
  • Time off
  • Recurring meetings and admin
  • Work demand
  • Capacity summary
  • Weekly overview
Five rows from the Work demand sheet, with the template's sample data. Dates are in 2026 and 2027.

The formula

How do you calculate team capacity?

Team capacity is the sum of each person's available hours: contracted hours, minus time off, minus recurring meetings and admin. Divide the hours of work planned by that number and you have utilization. Work it out per person as well as for the team, because a team total can hide one person at nearly double their hours.

The two formulas

Available hours = contracted hours - time off - meetings and admin

Utilization = assigned hours ÷ available hours

Available hours never go below zero. When someone has no available hours in a week, utilization can't be calculated, so the template marks the week over capacity if work is still assigned and "no available hours" if it isn't.

Worked example: the calculator's team

  1. Contracted hours: 6 people × 40 hours = 240 hours.
  2. Time off this week: 16 hours.
  3. Meetings and admin: 6 × 8 hours = 48 hours.
  4. Available hours: 240 - 16 - 48 = 176 hours.
  5. Work planned: 6 × 32 hours = 192 hours, so utilization is 192 ÷ 176 = 109%.

Measured against contracted hours, the same plan looks like 80%. That gap is why the template starts from available hours instead of a 40-hour week.

Per person: one week of the template's sample team

The week of November 9, 2026, as the Capacity summary sheet shows it, in hours.

PersonContractedTime offMeetings and adminAvailableAssignedUtilizationStatus
Ana, Designer4006342471%Within capacity
Ben, Developer401651936189%Over capacity
Chloe, Developer4007333091%Within capacity
Diego, Project manager40014262077%Within capacity
Elena, Analyst3204281243%Under capacity
Farid, QA engineer4005352057%Under capacity
Whole team232164117514281%61% of contracted hours

The team total is 81%, which looks comfortable. Per person it isn't: Ben took two days off but kept all 36 hours of his project work, so he is at 189%, while Elena and Farid are at 43% and 57%. Moving Ben's 17 extra hours to Elena and Farid, who have 16 and 15 hours to spare, would bring everyone to 100% or below, if they have the skills for it; if not, a deadline has to move instead.

Leave room

Why does planning to 100% of available hours fail?

Because a plan at 100% leaves no hours for anything unplanned. An urgent request, a task that runs over its estimate or a sick day then comes out of overtime or out of next week's plan, and next week starts behind. The fix is a plan that keeps your usual amount of unplanned work free.

Worked example: one developer, one week

She has 35 available hours: 40 contracted, minus 5 of meetings and admin. During the week, an urgent support request takes 3 hours and a task estimated at 12 hours takes 16. That is 7 hours nobody planned.

HoursPlanned to 100%Planned to 80%
Available3535
Planned work3528
Urgent support request+3+3
Task runs 4 hours over+4+4
Work that week4235
Result7 hours over: overtime or next weekFits in the week

What the example shows

  • At 100%, every surprise is a delay. The 7 unplanned hours become 7 hours of overtime or 7 hours of planned work pushed into next week. If next week is also planned to 100%, it starts 7 hours short, and the shortfall carries forward until someone works late or something is dropped.
  • 80% is this example's number, not a rule. It is simply the level that leaves room for 7 unplanned hours out of 35. Your number depends on how much unplanned work your team really gets.
  • Set your threshold from your own weeks. Add up the unplanned hours of the last few weeks and keep that much free. For example, 7 unplanned hours out of 35 means planning to 80%: set the over-capacity threshold on the Capacity summary sheet to 80% and the template flags anyone above it.

Plan with real data

How do you plan capacity with real data instead of guesses?

Replace the assumptions in the plan with measured hours. A spreadsheet starts from contracted hours and estimated meetings; work data shows how many hours people actually spend working at their computers, and where those hours go.

Intelogos is a workforce analytics platform that shows how work time is spent across apps and websites, without screenshots or keystroke logging, and lets managers ask questions about it in plain language. Here is what its workforce analytics adds to a capacity plan.

  • Expected hours from your real schedules

    Admins set work hours in Settings: a company policy with workdays and hours per day, plus custom policies for specific people or departments, such as a four-day week. Availability and Productivity are measured against those expected hours.

    Work hours settings
  • Time off that keeps the numbers fair

    People request time off in the Time Off module and managers approve it. Days covered by approved time off are left out of the Workday average, so a week of vacation does not pull it down.

    Time Off
  • Workday and Availability for every person

    Workday is the average amount of time tracked on a workday. Availability is the portion of the day the user was working, out of the total amount of time they were expected to work. Low Availability can mean time off, meetings or work away from the computer, so treat it as a question to ask, not a verdict.

    Availability KPI
  • The whole team in one table

    The Team page lists these KPIs for everyone you manage, grouped by department, manager, job title or project with group averages, and exports the table to CSV.

    Team page
  • Where meeting and admin time goes

    Time categories group tracked time by type of work, including Communication (messaging, email and calls), on the Dashboard and Profile pages: a check on the hours you entered on the Recurring meetings and admin sheet.

    Time categories
  • Questions in plain language

    On the AI Intelligence plan, Ask AI answers questions about your team's work data, such as "Is there anyone who might be at risk of burnout?"

    Ask AI

Intelogos doesn't take screenshots. Intelogos doesn't record what people type; it records only whether keyboard or mouse input happened. It doesn't estimate tasks or schedule project work either: the template does the planning, and Intelogos shows how the weeks really went.

Team Member
Time
Engagement
Productivity
Emma DavisEmma Davis
8h 48m
92%
87%
David RobertsDavid Roberts
7h 15m
85%
91%
Nina PatelNina Patel
6h 30m
78%
72%
Alex ThomsonAlex Thomson
4h 12m
45%
38%
Illustration of the Intelogos Team page, with sample data.

Download

Download the capacity planning template

One Excel workbook with seven sheets, filled with a sample team of six so you can see every formula working before you type over it. Enter a work email and your company size and the file appears right here.

What's inside

  1. 1. Instructions

    The five steps, the formulas, what each flag means and where to change the thresholds.

  2. 2. Team

    Name, role and contracted hours per week for up to 30 people, with part-time hours where they apply.

  3. 3. Time off

    Vacation, holidays and training: the person, any date in the week and the hours off.

  4. 4. Recurring meetings and admin

    Stand-ups, 1:1s, email and reporting, in hours per week for each person.

  5. 5. Work demand

    Each project a person works on, with estimated hours per week from the first week to the last.

  6. 6. Capacity summary

    Per person per week: contracted hours, time off, meetings and admin, available hours, assigned hours, utilization and a status.

  7. 7. Weekly overview

    The same result as a grid of people and 12 weeks, colored by status, with a whole-team row.

Formulas only, with no macros and no links to other files. Room for 30 people over 12 weeks; the over-capacity and under-capacity thresholds (100% and 70%) are settings you can change.

Get the editable files

A work email and your company size. No name, no call.

We store your email with the download request. See our privacy policy.

Using Google Sheets?

The .xlsx opens in Google Sheets: choose File > Import, select the file and pick Create new spreadsheet. It uses only functions Google Sheets also supports. See Google's guide to importing files.

FAQs

Frequently asked questions

Excel and Google Sheets, team and employee capacity planning, workload analysis, and what utilization to plan for.

Understand your team.
Drive better results.

G2
4.9+ review average

Join thousands of teams already using Intelogos to unlock their full potential with AI-powered workforce analytics.

No credit card required

Start your free trial

Get full access to all features for 7 days. Set up in minutes, see results next day.

  • Unlimited team members
  • All analytics plan features
  • AI-generated insights
Start 7-Day Free Trial
Personalized walkthrough

Schedule a demo

See how Intelogos can transform your organization. Get a tailored demo for your specific needs.

  • Custom implementation plan
  • Enterprise features overview
  • ROI analysis for your team
Talk to our team